Winchester Flood Defences
Flood Defence Improvement Works
When several public buildings adjacent to the River Itchen in North Winchester were deemed at risk of flooding, Hampshire County Council needed to address the situation.
With their expertise in this field, prominent building and civil engineering firm Mildren Construction Ltd were appointed to assist on the £668,000 project.
The brief was to improve the flood defences surrounding several important public buildings within close proximity to the river including the River Park Leisure Centre, St Bede’s School, Winchester School of Art and other surrounding public and private buildings.
The new defences consist of brick clad reinforced concrete walls, earth bunds and timber sleeper walls. Flood gates were also installed as part of the works, and will be closed as and when there is an increased risk of flooding to channel flood waters back towards to main River Itchen.
Development time
14 weeks
Project type
Framework
Works included
significant temporary works
Winchester Flood Defences
Winchester, UK