Junction Improvements
The project included improvements at two different junctions along the A3057 in Nursling. The main works being on the junction between Redbridge Lane, Bakers Drove and the A3057, and at the other one, the junction between Horns Drive, Nursling Street, and the A3057.
Works comprised:
- Installation of traffic signals at the A3057, Redbridge Lane and Bakers Drove junction.
- New highways layout at A3057, Redbridge Lane and Bakers Drove junction.
- Upgrading of the existing traffic signals at the A3057, Horns Grove and Nursling Street junction.
- New highways layout at A3057, Horns Grove and Nursling Street junction.
- Associated highway construction works, including site clearance, drainage, ducting and earthworks, for both junctions.
- Associated signage and road markings.
- Coordination of utility diversions.
-
48 weeksDuration